Public Criticism - Environmental Concerns
Case 79-2
| NSPE Board of Ethical Review Case
Study Taken from the National Society of Professional Engineers Board of Ethical Review Cases by the Murdough Center for Engineering Professionalism, Texas Tech University with permission from NSPE. All BER cases are available from the National Society of Professional Engineers, 1420 King Street, Alexandria, VA 22314-2794, Phone: 703-684-2800. Note: The NSPE Code referenced in this case is the one in effect during the year considered (the first two numbers in the case number) which is not necessarily the current code. For the current NSPE Code, see link below. Links! |
Other NSPE/BER Case Studies | NSPE
Code of Ethics | |
Facts:
Engineer A, the town engineer, and Engineer B, a consulting engineer retained by the town
council, collaborated on an assignment to make studies and determine final contours for an
existing sanitary landfill, taking into account final land use, environmental concerns,
surrounding land use, and topography. Engineers A and B jointly determine that the
existing landfill space will be exhausted at present rate of use in three years, or soon
thereafter. The town council had sought an alternate disposal location, but had not been
able to locate one. It then requested Engineers A and B to submit new designs for the
existing site at higher final contours in accordance with state environmental laws. After
several redesigns were not accepted, the town council requested Engineers A and B to
prepare a new design which resulted in an accepted solution, incorporating minimum
setbacks and maximum allowable slopes. This design would provide for a hill more than 100
feet higher than originally proposed. Engineer C, a resident of the town, publicly
contends that the higher level design concept would be environmentally unsound because
methane gas from the landfill would move into adjacent private property and that it would
pollute the nearby ground water. The issue stirred up considerable local publicity and
controversy. Engineer C has publicly questioned whether Engineers A and B should have
agreed to the higher intensity use of the site.
Questions:
1. Did Engineers A and B act ethically by participating in the design approach requested
by the town council?
2. Did Engineer C act ethically in publicly challenging the design approach adopted by Engineers A and B?
References:
Code of Ethics Section 2 "The Engineer will have proper regard for the safety,
health, and welfare of the public in the performance of his professional duties. If his
engineering judgment is overruled by non-technical authority, he will clearly point out
the consequences. He will notify the proper authority of any observed conditions which
endanger public safety and health." Section 2(a) "He will regard his duty to the
public welfare as paramount." Section 2(c) "He will not complete, sign, or seal
plans and/or specifications that are not of a design safe to the public health and welfare
and in conformity with accepted engineering standards. If the client or employer insists
on such unprofessional conduct, he shall notify the proper authorities and withdraw from
further service on the project." Section 12 "The Engineer will not attempt to
injure, maliciously or falsely, directly or indirectly, the professional reputation,
prospects, practice, or employment of another engineer, nor will he indiscriminately
criticize another engineer's work. If he believes that another engineer is guilty of
unethical or illegal practice, he shall present such information to the proper authority
for action."
Discussion:
It is axiomatic that an engineer's primary ethical responsibility is to follow the mandate
of 2(a) to place the public welfare over all other considerations. In this case there
would be no doubt of the result if we accept as fact that the higher density use of the
site would actually be detrimental to the environmental concerns of the citizenry. In that
event it would clearly be the duty of Engineers A and B to decline to follow the town
council's decision to proceed with the project. But, of course, the case is not that
simple. If we assume, as we must, that Engineers A and B are of the sincere opinion that
the approach desired by the town council will not jeopardize the public health of the
community, we are led into a recognition that this is the kind of situation the
engineering profession must face increasingly as public awareness of environmental
concerns increases. There is no finite answer to the balance or "trade-off"
which is involved in the overall concerns about Case No. 79-2 environmental dangers for
particular projects. At the federal, state, and local levels there is a growing body of
law and regulation designed to establish governing criteria. But despite these efforts
professional judgment will be the final arbiter of the best balance between society's
needs for certain facilities and the level of environmental degradation which may be
unavoidable in filling those basic needs. For example, the federal Environmental
Protection Agency has recently published proposed guidelines entitled, "Landfill
Disposal of Solid Waste." (Federal Register, March 26, 1979.) Those guidelines are
designed ".... to define the level of health and environmental protection which a
land disposal facility must achieve to avoid designation as an 'open dump'." And they
further stipulate that the test for compliance with the criteria is whether ". .
.there will be no reasonable probability of adverse effects on health or the environment
associated with disposal of solid waste at a facility. This is a case-by-case decision
which requires cognizance of the particular circumstances found at each site." We
cited the above statements not to indicate that the technical data are either correct or
controlling for a particular project, but rather to confirm that there cannot be a
clear-cut resolution in advance to resolve differences of opinion in such matters.
Certainly Engineers A and B should consider the technical data in the guidelines, whether
they be those cited here or others published by various public authorities or technical
experts in the relevant field of knowledge. But, as quoted above, each project requires a
case-by-case analysis and judgment. It should be added that these decisions in the public
arena are subject to open public debate and resolution by appropriate public authority.
Engineer C was acting within the intent of the code in raising his concern. However, in
such a matter of important public policy, if, after due consideration of his views and
those of others, the decision should be to proceed with the proposed design of the
expanded landfill, all involved should accept that each engineer had acted in conformance
with the code. That there are conflicting public views between engineers in this case
should be of no concern. As we observed as long ago as Case 63-6, "There may...be
honest differences of opinion among equally qualified engineers on the interpretation of
the known physical facts." And with regard to 12 of the code, we noted in the earlier
case that a related ethical principle then obtaining "...does not prohibit ...public
criticism; it only requires that the engineer apply due restraint. . .in offering public
criticism of the work of another engineer; the engineering witness will avoid
personalities and abuse, and will base his criticism on the engineering conclusions or
application of engineering data by offering alternative conclusions or analyses." Our
conclusion in that case was that "it is not unethical for engineers to offer
conflicting opinions on the application of engineering principles, or to criticize the
work of another engineer, at hearings on an engineering project, in the interest of the
public, provided such criticism is offered on a high level of professional
deportment." Along the same line, see Case 65-9.
Conclusions:
*1. Engineers A and B acted ethically by participating in the design approach requested by
the town council.
2. Engineer C acted ethically in publicly challenging the design approach adopted by Engineers A and B.
*Note: This opinion is based on data submitted to the Board of Ethical Review and does not necessarily represent all of the pertinent facts when applied to a specific case. This opinion is for educational purposes only and should not be construed as expressing any opinion on the ethics of specific individuals. This opinion may be reprinted without further permission, provided that this statement is included before or after the text of the case. Board of Ethical Review Louis A. Bacon, P.E. Robert R. Evans, P.E. James G. Johnstone, P.E. Robert H. Perrine, P.E. James F. Shivler, Jr., P.E. L.W. Sprandel, P.E. Donald C. Peters, P.E., chairman.
| BACK TO TOP |
Last Update: 12/19/01
Site Designed and Created by: RCG550@door.net
© 1997 National Society of Professional
Engineers
(What does this
Copyright mean?)